May 27, 2023 |
During the past two weeks, the contractor completed all landscape restorationand placed the final lift of Hot Mix Asphalt surface on all streets! Following asphalt placement, the contract installed pavement markings for crosswalks and stop bars. The project team also completed various punch list items and is awaiting the delivery of basketball hoops and benches for Highland Hill Park.
Next week, the general contractor will complete the remaining pavement markings and remove all remaining road construction barricades and inlet filters from the job site. Inlet filters remove sediment or construction material from storm water runoff before it enters the storm drain. We appreciate your patience as we wrap up construction and create safe, new drivable roadways. |