Work is expected to resume in the spring and includes concrete sidewalk and curb removal and replacement, removal and replacement of the existing basketball court and path in High Hill Park (North), ground stabilization on the local streets followed by asphalt pavement, and landscape restoration.
Project Updates
November 12, 2022 |
This week, the contractor completed the paving of all streets in the southern section of the project (streets south of Harnish Drive). Crews were also able to complete the landscape restoration in this area as well.
Over the next two weeks, crews will perform general clean up and temporary patching of various sidewalk in the north section of the project area (locations north of Harnish Drive). Please note that improvements will resume on streets north of Harnish Drive in Spring of 2023. |